What a cultivation drawing set should contain, sheet by sheet
The short answer
A commercial cannabis cultivation set runs to roughly 18 to 30 sheets. It opens with floor plans, then gives each building system a placement plan and a details sheet: canopy and benching, top light, under canopy light, airflow, dehumidification and fertigation, and closes with room elevations. A detailed set adds isometric and exploded views of the irrigation and the water room, and a title sheet carrying the pipe fitting and accessory schedules. If a set has fewer sheets than systems, something has been left to the installer to decide on site.
The 18 sheet approval set
This is the set a client signs off before anything is ordered. It is organised by system, and the numbering tells you what you are looking at: A sheets are architectural, Q sheets are equipment, and the second digit groups the system.
| Sheet | Title |
|---|---|
| A1.01 | Proposed plan |
| A1.02 | Floor plan, cultivation area |
| A1.03 | Floor plan, processing area |
| Q1.00 | Cultivation equipment plan |
| Q1.01 | Canopy equipment plan, resting position |
| Q1.02 | Canopy equipment plan, roll positions |
| Q2.01 | Top light equipment placement plan |
| Q2.02 | Top light equipment details |
| Q2.03 | Top light equipment details |
| Q3.01 | Under canopy light placement plan |
| Q3.02 | Under canopy light details |
| Q4.01 | Fan equipment placement plan |
| Q4.02 | Fan equipment details |
| Q5.01 | Dehumidifier placement plan |
| Q5.02 | Dehumidifier details |
| Q6.01D | Fertigation equipment placement plan |
| Q6.02D | Fertigation equipment, Dosatron |
| Q9.01 | Elevations |
Two things in that list are worth pointing at. The canopy plan appears twice, at the resting position and at the roll positions, because rolling benching that fits on paper can foul a fan or a downspout once it moves. And every system has two sheets, a placement plan and a details sheet, because the position and the part number are different decisions made by different people.
The 30 sheet detail set
Where the approval set settles what goes in the room, the detail set settles how it gets built. It adds elevations per room, isometric views, exploded irrigation details and a full water room package.
| Range | Sheets | Covers |
|---|---|---|
| CULT0.01 | 1 | Title and parts: pipe fitting, accessory, pipe and flex pipe schedules, plus the sheet list |
| CULT1.01 to 1.03 | 3 | Cultivation plan view and hallway and room elevations |
| CULT2.01 to 2.05 | 5 | Flower rooms: plan, elevations, two isometrics, split table irrigation exploded, type 1 table detail |
| CULT3.01 to 3.04 | 4 | Veg and moms: plan, elevations, isometrics, racking irrigation detail |
| CULT4.01 to 4.05 | 5 | Moms: plan, two elevation sheets, isometrics, type 2 table detail |
| WR1.01 to 1.03 | 3 | Water room floor plan and elevations |
| WR2.01 to 2.02 | 2 | Water filtration, including an exploded view |
| WR3.01 to 3.03 | 3 | Fertigation and valve manifold |
| WR4.01 to 4.06 | 6 | Batch tanks: elevations, isometric, colour coded perspective, exploded detail |
Six sheets on batch tanks alone looks like a lot until the install. An exploded detail is the sheet a plumber builds from, and it is the difference between a water room that goes together in the order it was drawn and one that gets taken apart twice.
How to tell a real set from an equipment list with a border
- Each system has a placement plan and a details sheet. One sheet per system means the part numbers are missing or the positions are.
- The canopy is drawn at every position it can occupy, not just the one it ships in.
- Fertigation appears as a piping and instrumentation diagram, not only as a plan. A plan shows where the tank sits; the P&ID shows the order of operations.
- There are schedules with part numbers and quantities, not categories and counts. A real schedule has lines like 196 one inch socket elbows on it.
- Elevations exist. Everything in a cultivation room has a height, and heights are where the conflicts are.
- The title block names who drew it and who checked it.
Common questions
How many drawings are in a cannabis cultivation design set?
An approval set that settles what goes in each room runs to around 18 sheets. A detail set that settles how it is built, including room elevations, isometrics, exploded irrigation views and a water room package, runs to around 30. Both of those are real sheet counts from released EES sets.
What is the difference between a placement plan and a details sheet?
A placement plan fixes where equipment goes in the room and, for fans, which way it throws. A details sheet carries the schedule, the part numbers and the elevations for that same system. They are separate because the two decisions are made by different people at different times.
Why is the canopy drawn twice?
Rolling benching occupies more than one position. A grid that clears a fan, a column or a downspout at rest can foul it once rolled, so the set draws the resting position and the roll positions as two sheets.
Do I need elevations for a grow room?
Yes. Lights, fans, irrigation mains, dehumidification and racking all occupy height, and conflicts between them are vertical rather than horizontal. A set without elevations has not checked whether the fans clear the benching at its highest tier.
How we put this together
The sheet lists below are the actual drawing numbers and titles from two released EES sample sets: an 18 sheet design approval set and a 30 sheet cultivation and water room set. Both are published in full on our Technical Services page.
Elevated produces these sets. The examples are our own drawings.